The short answer
Yes. Winter does not rule a roof window out, but the roof must never be left open to the weather. The roofer waits for a suitable day, prepares everything before the covering is lifted, and closes the opening with a temporary cover if the job is not finished. Sealants and adhesives have working temperatures, so the product data sheets are checked.
Choosing the weather window
Met Office averages for South Farnborough, from 1991 to 2020, show rainfall of about 715 mm a year spread over 118 wet days, with around 53 air-frost days. That is a typical year, not a forecast, but it shows that dry days are common even in winter, and they are what the work depends on.
The job is planned around the forecast, not the calendar. A new opening needs a spell of dry weather long enough to strip the covering, frame the rafters, set the window and seal the flashing, and it is better to wait for that than to start in a doubtful hour. A swap of an existing window needs less time open, so it fits shorter windows.
Rain is the main limit, but frost and wind count too. Frost can make tiles and slates slippery and damage sealants that have not cured, and strong wind makes handling a large pane and working at the edge unsafe. The forecast is read the night before and once more in the morning, and the job does not start if it looks wrong.
If a day is lost, the job moves. That is better than a rushed fit that leaks. Delay is a normal part of winter work, and the plan covers what happens to a postponed visit.
Temporary cover and keeping the house dry
Ahead of lifting the covering, a waterproof cover is cut to size and kept ready for the opening. If the weather turns, or the job runs past the light, the cover is fixed down and the roof is safe until the next visit. The cover is held in place against wind and checked at the end of the visit.
The room below is protected as well. Furniture is moved or covered, dust sheets go down, and the floor under the opening is cleared. If a bedroom is below, it may be sensible to plan for the room to be empty on the day. Insulation and linings are kept dry, because damp insulation loses its value and can trap moisture in the roof.
The sequence helps. Window, flashing kit, insulation collar and lining parts are all on site and checked before work begins, so nothing is missing once the roof is open. The opening is made, the frame goes in and the flashing is lapped promptly, with weatherproofing ahead of any inside work.
If you are worried about rain getting in during a job, ask for the plan in advance. Our guide to a leaking roof window covers the faults that follow a poor fit.
Sealants, adhesives and cold
Cold affects materials as well as people. Sealants, adhesive tapes and some membranes have a range of working temperatures, and they may not bond or cure below the lower limit. The product data sheet gives that range, and we follow it. Where the day is too cold for a product, the job waits or a different product is used.
Condensation and damp are a risk too. A cold roof and a warm room produce moisture on cold surfaces, and a fresh opening is a place where it collects. A well-sealed lining and a continuous insulation collar guard against it, and BS 5250:2021 is the reference for how a roof manages vapour. Our answer on condensation on a roof window explains the signs.
Plaster and filler need warmth to dry. Where the inside finishing involves wet trades, a cold house dries slowly, and heating the room or choosing dry lining helps. A plastered reveal that has not dried can mark and crack.
None of these points stops a winter job. They shape how it is done, and a roofer who knows the product limits can work through most of the season.
Inside finishing and the order of work
The inside is the last stage and the one that takes the weather least. Once the window is set and weathertight, the lining, the insulation and the finish can be completed under cover, even on a wet day. It is common to separate the visits: one for the roof, in a good forecast, and a second for the finishing.
That order protects the house. The roof side is closed before the room is touched, so a change in the weather does not undo the work. Lining and insulation then go in dry, the vapour seal is taped, and the reveal is boarded or plastered.
We photograph each stage, including the collar and the seal before the lining goes up, and you can see what was done. The photos are useful later for a surveyor or a buyer, and they show that the work was done properly in difficult conditions.
Scaffold is the other thing to check in winter. Scaffold across a public road needs a Highways Act 1980 s169 licence, and the notice period can affect the date. Our answer on how long a roof window takes to fit covers that. See roof windows and skylights for the full service.